top of page
Facts and Assumptions: Text

FACTS AND ASSUMPTIONS

​IRP 1:

  • A flat roof design will be used in accordance with the university master plan

  • Roofing materials used include: 20 gauge metal decking, 2" fiberboard thermal insulation, a waterproof membrane, drop ceiling, suspended steel channel system, HVAC system, lighting components, and a roof decking

  • Floor materials used include 1.5" terrazzo tile, drop ceiling, suspended steel channel system, HVAC system, lighting components, and a floor decking

  • A slab of 3.5 inches of lightweight concrete will be used for the ground floor decking

  • Vulcraft was used to chose the roof and floor decking 

  • Decks will be 3 eight ft spans at a length of 42 ft

  • The facility will include: dance floor/auditorium, stage, storage, and bathrooms

  • Beams and columns are wide flange and truss members are double angle

  • All columns are pinned at the foundation

  • All roof/floor beams and joists have simple connections

  • All truss connections are pinned

  • Parapet dead loads were calculated using ASCE C3.1-1a

  • Snow load for the New York area was found using ASCE Figure 7.2-1

  • Risk category III was used considering the building poses a high risk to human life in the event of failure (ASCE Table 1.5-1)

  • Exposure B was selected considering the mean roof height is less than 30 feet

  • Ground floor live loads were found using ASCE Figure 4.3-1

  • It is assumed that the snow load will be greater than 20 psf, thus the roof live load can be ignored

  • Assuming a Risk Category III, Exposure B, and a mean height of 20 ft, the wind loads can be calculated

IRP 2:

  • Self weight of roof joists RJ1 =15plf

  • Both roof trusses are identical due to symmetry

  • Roof truss has a height of 4 feet 

  • Include truss member self weight in the dead load case in VA

  • Load case combinations 4 and 5 do not apply since they are not apart of the lateral load carrying system

  • Maximum Pu of a member (ie. Top Chord T5) is used to represent all members as the same Pu value (ie. Top Chords T1-8).

  • Pin-Pin Connection, so the effective length factor, K, equals 1.0

  • All truss members are equal leg double angles

  • The separation of the members is 3/8"

  • All beams are made from A36 Steel

  • Ae=0.75Ag

  • The truss may not exceed a snow load deflection greater than L/240

  • A maximum of 4 unique members can be included

  • The cost per pound of Steel is $0.50

  • The cost per truss node is $20

  • The cost per unique member Fabrication is $100

  • The cost per ton for Fabrication is $750

IPR 3:

  • Service load end reactions are applied from the beams and joists to the girders and then from the girders and beams to the leaning columns.

  • For lateral bracing members, assume the leaning columns are pinned at the base (foundation).

  • Governing LCC may change as you go down the load path.

  • Pass only service (unfactored) reactions down to the next member.

  • It is necessary to cope the flanges to facilitate connecting them into members

  • Nominal floor beam and girder depth should be at least 21 inches for making room for mechanical ducts.

  • For deflections, the member self-weight is not included.

  • Cambering can be used for dead load deflections only (total load criteria). Camber cannot be applied to live load deflections.

  • Loads are not factored when calculating deflections.

  • Select either of the two types of connections for beam to column/girder and use for FG1 to column connection.

  • Once the initial beams and girders are chosen, self-weight is included and load effects are recalculated.

  • Beams are continuously supported by the floor deck and have an unbraced length of zero feet (Lb= 0) due to spot welds to the deck along the length of the beam.

  • For girders, use an unbraced length equal to the beam spacing.

  • Column designs are pin-pin connections, so k=1.0

  • facebook

©2019 by Shearing Engineering LLC. Proudly created with Wix.com

bottom of page